Key takeaways
- Supplying an item moves the purchase and usually the product warranty to the client, but the builder still owns the installation and the compliance of the building.
- The written contract decides the allocation first, so client-supplied items should be dealt with in a schedule rather than left to a general clause.
- A builder who has concerns about a supplied product should raise them in writing before installation and say what is recommended instead.
- Delays caused by late or incorrect supplied items should be recorded as they happen, with the messages that show when the client was told.
- The installation records for every supplied product are the evidence that separates a product failure from a workmanship failure when a defect appears.
Clients often want to buy the tapware, the light fittings, the appliances or the stone benchtop themselves. Some of them have found a better price online, some want a particular look, and some are simply trying to keep the total under control. The builder is usually happy to save the money on the client’s side, and the item goes onto the job with a short note that the client has bought it. That short note is where the risk is most often left unallocated.
The question this article answers is simple to ask and harder to settle on a live job. When the client supplies the material or fitting, who carries the risk if it is wrong, late, incompatible with the design or the cause of a defect later on? The answer depends on the contract and on what the builder did or did not say at the time, not on who paid for the item. The sections below set out the mechanism, so that a builder can reason about a supplied item that the contract never anticipated.
Nothing in this article is legal advice, and it does not replace reading the contract that governs your job. It is a working explanation of where the risk tends to land, and what to put in writing so that the answer is not a dispute at the end of the job.
What changes when the client supplies the item
Ownership of the item changes hands at purchase, but responsibility for the building work does not. The builder still installs the product into a building that has to meet the requirements that apply to it, and the builder still delivers the workmanship the contract promises. Supplying the product moves the purchase, and usually the product warranty, to the client. It does not move the obligation to install competently or to tell the client when the product will not work in the place it is going.
This is the point most builders miss. The client may have bought the item from a supplier who is responsible for the product itself, if it fails in normal use. The builder is responsible for the installation and for the surrounding work. When the two interact, as they do with a waterproofing product, a sealed window system or a heavy stone benchtop fixed to a light frame, the defect rarely stays in one column. The product fails, but the water gets in through the builder’s junction, and the question becomes whose work caused the damage.
The contract decides first
Start with the written contract. The NSW Government’s guidance on contracts for home building work is the official reference for what a written contract should cover, and the contract for your job should say how client-supplied materials and fittings are handled. Look for the clauses that deal with supply, with the builder’s responsibility for materials, with variations and with what happens when an item is delayed. Where the contract is silent on a point, the default position is harder to argue than most builders expect, so the safest course is to settle the point in writing before work starts.
A contract that says nothing about client-supplied items is not a neutral document. It leaves the builder to argue, after the event, that the client carried the risk of an item they chose. That argument is easier to win when there is a dated email or a signed schedule that records the client’s choice and the builder’s warning about it. Without that record it becomes a question of recollection, and the party who has to pay for the remedial work is usually the one holding the site.
The sequence below shows where the decisions are made on a supplied item, from the moment the client chooses it to the handover. Most of the protection is built in the first two stages, which is why it is so much cheaper to settle the allocation early.
Where the risk is decided on a client-supplied item
- Selection and sign-offThe client chooses the item, and the builder records any concern about its suitability in writing.
- Delivery and inspectionThe item is checked against the order, the design and the product data sheet before it is accepted on site.
- InstallationThe builder fixes the item using the manufacturer’s method and records what was installed, where and how.
- Handover and recordsThe warranty, the schedule and the installation evidence are handed over together so the allocation can be shown later.
Compliance stays with the builder
A supplied item still has to meet the requirements that apply to the building. A product that is not suitable for the location, a fixing that is not rated for the load, or a window that does not meet the energy or safety requirements of the job can make the whole job non-compliant, whoever bought it. The building’s compliance is the builder’s job to protect when the builder installs the product. The client can decide to buy the item, but the builder should not install an item that the builder knows, or ought to know, will not meet the requirement.
The practical step is to check the product against the design and the requirements before it is fixed in place, and to say so in writing if there is a concern. A short note that says the builder has reviewed the product against the design and believes it may not be suitable for a particular location, together with what the builder recommends instead, is a record that protects the builder. A builder who installs a product without raising a concern, and whose concern would have been obvious on a check, is in a very different position from one who raised it and was overruled.
Be careful with the words. Many products are suitable for one location and not another, and the product data sheet is the document to read, not the sales description. Where a product is sold as suitable for a wider range of uses than the design allows, that gap is exactly where the warning belongs.
The mistake that costs the most. Installing a client-supplied product without raising a concern in writing, when the builder could have seen the problem on a check. When it fails, the builder carries the remedial cost, and the only record of the decision is a verbal understanding that the client chose the item.
Delay: when the item arrives late, or not at all
Client-supplied items are a common cause of programme delay, and the delay is rarely the builder’s fault. A window package that was ordered too late, a fitting that arrives with the wrong finish, or a stone benchtop that does not fit the template all push the trade sequence back. The consequences fall on the builder through the trades booked around the item, the crew standing idle and the extended site costs, while the client often sees the delay as the builder’s failure.
The protection is to put the dates in the programme and to tie them to the client’s obligations. Agree the date by which the item must be on site, the date it must be confirmed, and what happens if it is not. Record the delay as it happens, with the messages that show when the client was told and when the item was expected. Where the contract provides for an extension of time for delays caused by the client, the record is what lets the builder use it. Without the record, the same delay becomes a dispute about who was late.
Building Commission NSW has published an article on rising fuel costs for trades, which deals with contracts, insurance and compliance together. Cost pressure on a job tends to make both sides look for savings in the supply chain, and that is when client-supplied items come into the job late and without the paperwork to match. It is worth reading the article alongside the contract before you accept a client-supplied item in a tight programme.
Defects that trace back to a supplied product
When a defect appears, the first question is what caused it. A seal that fails because the sealant was not compatible with the substrate is the builder’s failure. A seal that fails because the product itself was defective is the supplier’s failure, and the builder is not responsible for the product. The third possibility is the most common: the product was fine, but the builder installed it in a way the manufacturer did not allow, or in a location the product data sheet does not cover.
The Building Defects Library published by Building Commission NSW is a useful reference for describing what a defect looks like, and it helps the builder and the client talk about the same thing. The classification of the defect matters, because it affects how seriously the remedy is taken. Waterproofing problems, for example, could be classified as a major defect, and a supplied membrane that fails in a wet area is a case where that classification may apply. The distinction is covered in major and minor defects in NSW.
Keep the installation records for every supplied product. The photograph of the substrate before it was covered, the batch or serial number, the fixing method and the manufacturer’s instructions as they were on the day are the evidence that separates a product failure from a workmanship failure. Without them the builder is arguing from memory, and memory is rarely kind to the party who has to prove a negative.
Warranties and what a supplied product does to them
The warranty on a client-supplied product usually belongs to the client, and it runs between the client and the manufacturer or retailer. The builder’s own obligations sit alongside that, not inside it. The builder may still owe the client a remedy for defective workmanship, and the client may still expect the builder to deal with a failure the client has already taken up with the supplier. The two processes can run in parallel, and the builder should not assume that a manufacturer’s warranty removes the builder’s exposure.
Where the builder is asked to deal with a warranty claim for a product the builder did not supply, the builder should make the scope clear. Say what the builder will do, such as inspecting the installation and reporting on whether it was done in line with the manufacturer’s instructions, and what the builder will not do, such as accepting responsibility for the product. A short written response protects both parties and stops a goodwill favour becoming an open-ended obligation.
Writing the allocation into the job
The allocation is best settled in a single schedule that sits with the contract. List each client-supplied item, the date it is due, the person responsible for confirming its suitability, the warning the builder has given, and the client’s acknowledgement of that warning. Where the client has chosen an item against the builder’s advice, the schedule should say so in plain words. That is not an attempt to shift every risk to the client. It is a record of who decided what, and why.
Before any client-supplied item is agreed, run through the checks below. If one of them cannot be ticked, the item is not ready to be accepted onto the job.
Before you agree to install a client-supplied item
- The contract or a signed schedule says who supplies, who checks and who carries the risk for the item.
- The item has been checked against the design and the product data sheet for the location it is going into.
- Any concern about suitability has been raised in writing, with what the builder recommends instead.
- A delivery date is agreed, and the programme shows what happens if the item is late.
- The client has acknowledged in writing any warning the builder gave about a choice made against advice.
- Photographs of the substrate and the installation are kept before the surfaces are covered.
- The warranty documents and the product details are filed against the job, and the client knows where they are.
Treat variations for supplied items the same way as any other variation. If the client wants a change that affects the installation, such as a different fixing system that the builder did not allow for, the change should be documented before the work is done, with the effect on time and cost stated. A verbal agreement to absorb the cost of a change to a client-supplied item is the kind of concession that becomes a precedent on the next job.
Worked example: a builder in regional New South Wales
Consider a builder in regional New South Wales who agreed to install a set of client-supplied sliding doors on an extension. The client bought them online, and the builder raised a concern about the frame size against the opening, which the client waved away because the supplier had confirmed the measurements. The doors arrived with a frame that was slightly out of square for the opening, and the installation took longer than planned. The builder completed the installation and the client was happy at handover.
Some months later the doors began to leak at the head during heavy rain, and the client blamed the builder. The builder’s file had a dated email with the concern, the client’s reply and a photograph of the frame before installation. The builder was able to show that the installation followed the manufacturer’s fixing method, that the leak traced to a frame that was not square, and that the concern had been raised in writing before work began. The conversation moved from whether the builder was responsible to what the builder would do to help, and the builder offered to investigate the frame with the supplier at the client’s cost. That is a very different outcome from a builder with no record at all.
The lesson is not that the builder should refuse client-supplied items. It is that a concern raised early, in writing and tied to the design, changes the question from whose fault it is to what the remedy is.
Where to check the current position
The rules on contracts, compliance and defects change, and the examples in this article describe the mechanism, not the current requirement. Check the NSW Government guidance on contracts for home building work before you finalise a contract that includes client-supplied items. Check the Building Defects Library when you need to describe a defect accurately. Where a question turns on the specific requirement for a product, the product data sheet, the design documents and the relevant official requirement are the sources to rely on, not a summary of them.
If a dispute does arise, get advice from a solicitor who works with building contracts before you make any offer or admission. The record you have built while the job was underway is usually what decides the outcome, and it is far cheaper to build it at the start than to rebuild it afterwards. The broader picture of how defect responsibility runs after handover is covered in the defect liability period in NSW.
The wider obligations that sit around a licensed builder, including the continuing professional development that keeps a licence current, are set out in the PointCPD guide to how NSW builder CPD works.
Whatever the item, the rule is the same. Settle the allocation before the item goes in, write the warning down, and keep the record that shows who decided what.
Questions builders ask
If the client buys the product, am I still responsible if it fails?
It depends on why it failed. A product defect usually sits with the supplier or manufacturer, but a failure caused by how the builder installed it, or by a location the product is not suited to, is still the builder’s responsibility. Installation records are what separate the two.
Can I refuse to install a product the client has chosen?
You can refuse to install a product you believe will not meet the requirements that apply to the building. Put the concern in writing, explain what you recommend, and keep the client’s reply. Refusing without a reason on file can cause as much trouble as installing a product you should have questioned.
What should the contract say about client-supplied materials?
It should say who supplies each item, who checks it against the design, when it must arrive, who is responsible for any delay it causes, and how a warning about suitability is recorded. Where the contract is silent, settle these points in a signed schedule before work starts.
Does a manufacturer’s warranty protect the builder?
Not in the way many builders expect. The warranty runs between the client and the manufacturer or retailer. It does not remove the builder’s obligations for the installation, so the builder should not assume the warranty closes the question when a defect appears.
What happens if a client-supplied item arrives late and holds up the job?
The delay can be the client’s responsibility if the contract allocates it that way, but only if you can show when the item was due and when you were told it would be late. Record each message and date as it happens, and tie the delay to the programme.
Where do I check the rules on defects and contracts?
Start with the NSW Government guidance on contracts for home building work, and the Building Defects Library from Building Commission NSW. For a question that turns on a specific requirement, check the official source for that requirement and the product data sheet, and get legal advice before you make any admission.
Sources
- Contracts for home building work · NSW Government · 2026-04-29
- Rising fuel costs: what trades need to know about contracts, insurance and compliance · Building Commission NSW · 2026-04-28
- Building Defects Library · Building Commission NSW · 2025-06-25
Published 26 October 2026. General information for builders, not legal, financial or engineering advice for a specific job. Check current requirements with the relevant regulator or standard before relying on them.