Free template Safety and WHS

Free construction risk assessment template and risk register

A project-level risk register with a 5x5 matrix: list every hazard across the job, rate it, control it with the hierarchy of control, and review it as the job changes.

The short version

A risk assessment lists the hazards across a job, rates each risk by likelihood and consequence, and records the controls that bring it down, working through the hierarchy of control: eliminate, substitute, isolate, engineer, then administrative controls and PPE. Keep it as a living register and review it when the work, the site or the people change, or after an incident.

  • No sign-up
  • Free for commercial use
  • Add your own logo
  • Updated 14 Sep 2026

Reviewed by Daniel Betros, Licensed Building Practitioner

Animated walkthrough · 7 steps

How to do a construction risk assessment

Seven steps that follow the identify, assess, control, review cycle in the national code of practice.

1 / 7
  1. Say what the assessment covers: the whole project, a stage, or an activity. Name who prepared it and who was consulted. A register nobody helped write is a register nobody follows.

  2. Walk the site, read the plans, talk to the trades, check past incidents. List each hazard and who could be harmed: workers, other trades, the public, neighbours.

  3. Use the matrix to rate likelihood and consequence. This shows where the real risks are, so effort goes where it counts.

  4. Eliminate the hazard if you can. If not, substitute, isolate or engineer it out, and only then rely on procedures and PPE. Record the controls against each hazard.

  5. Rate the remaining risk with controls in place and put a name against each control. If it is still high, the controls are not enough.

  6. High-risk construction work needs a SWMS. Note which SWMS or JSA carries each control on site.

  7. Review at each new stage, when methods or trades change, after incidents and near misses, and if a control is not working. Record every review.

A risk register is the map of everything that could go wrong on a job, and what you are doing about each one. It is the document that tells you which SWMS you need, which trades have to coordinate, and where supervision should concentrate. This template gives you the register, a 5×5 matrix, the hierarchy of control and a review record in one file.

Where a risk assessment fits

The WHS risk management process has four steps: identify hazards, assess the risks, control them, and review the controls. The risk register is where those four steps are written down for a project. Below it sit the documents workers use every day: the SWMS for each high-risk construction activity, JSAs for other tasks, and Take 5 checks at the work face.

Step 1: identify the hazards

Good hazard identification uses several sources, not just memory:

  • The plans and specification: heights, excavation depths, heavy elements, site access and boundaries.
  • The site itself: slope, soil, overhead and underground services, neighbours, traffic, the public.
  • The people doing the work: trades know where their work goes wrong. Consulting them is also a legal duty.
  • Past incidents and near misses: on your jobs, and in the regulator’s safety alerts.
  • Materials: safety data sheets, silica-containing products, asbestos in existing buildings.

Step 2: assess the risk

The matrix combines how likely harm is with how serious it would be. It is a tool for judgement, not a calculation. Its value is in making a team agree which risks are serious, and in showing that the controls reduced them. Rate each hazard before controls, then again with controls in place. If the rating after controls is still high or extreme, the controls are not good enough and the method needs to change.

Step 3: control it, from the top down

LevelControlSite example
1EliminatePre-fabricate roof trusses and wall frames on the ground; design out work at height
2SubstituteScore-and-snap tools instead of power saws on fibre cement; lighter block units
3IsolateExclusion zones around plant; fencing between the site and the public
4EngineerEdge protection, scaffold, trench shoring, dust extraction, residual current devices
5AdministrativeSWMS, permits, training, supervision, signage, work scheduling
6PPEHarnesses, respirators, hearing and eye protection, hi-vis

The law requires you to eliminate risks so far as is reasonably practicable and, where you cannot, to minimise them by working down this order. Administrative controls and PPE are the least reliable because they depend on people doing the right thing every time, so they should back up higher controls rather than stand alone.

Step 4: review it

A risk register written at tender and never opened again does not protect anyone. Review it at each new stage, when methods or trades change, after incidents and near misses, when a control is not working, and when workers raise a concern. Record the review in section 6, even when nothing changes; it shows the register is alive.

Who should be involved

The builder or principal contractor owns the project register, but it should be written with the people doing the work. Subcontractors bring knowledge of their trade’s hazards; the health and safety representative, if there is one, must be consulted; and the designer may be able to eliminate hazards before anyone is exposed to them. On a construction project, the register feeds straight into the WHS management plan.

Common mistakes

  1. Every risk rated medium. If nothing is high, nothing gets priority. Be honest about the serious ones.
  2. PPE as the first control. Look up the hierarchy before reaching for a harness.
  3. No owners. A control without a name against it is a wish.
  4. No link to what happens on site. Each control should appear in the SWMS or JSA the crew actually uses.
  5. Written once, never reviewed. Stages change. So do risks.

Worked example: a two-storey home

For a typical two-storey brick veneer home on a sloping suburban block, the project register might start with these high-rated risks and their key controls:

HazardKey controlsDocuments
Falls from upper-floor slab edges, stair voids and roofPerimeter scaffold with edge protection from first-floor frame; void covers; roof edge protection before roofingScaffold SWMS; roofing SWMS; scaffold register
Excavation for the cut and retaining wallsEngineer-designed batters; services located; no one in the cut while plant worksExcavation permit; earthworks SWMS
Mobile plant and deliveries on a steep, tight siteTraffic plan; set-down area on the level section; spotter for reversing; pedestrian path separatedTraffic management plan; plant pre-starts
Silica dust from cutting masonry and fibre cementWet cutting or extraction; cutting station; respiratory protectionBricklaying and cladding SWMS
Overhead service line to the neighbourClearance zone marked; tipper and concrete pump positions planned; network operator consulted if neededSite plan; pump SWMS

Each line then points to the document where the control lives on site. That link is what turns the register from an office document into a site document.

Who writes what

The builder or principal contractor owns the project risk register and the site-wide controls: fencing, scaffold, traffic, amenities, emergency arrangements. Each subcontractor owns the risks of their own work method and writes the SWMS for their high-risk construction work. The builder’s job is to make sure the two fit together, especially where trades interact: the roofer and the scaffolder, the concreter and the plumber, the crane and everyone underneath it. Coordination between businesses is a legal duty, and the register is where overlaps show up.

Preview the full Construction risk assessment and risk register template

Every section, field and check in the download, exactly as it prints. Edit the Word version to add your logo, delete what does not apply and add your own site-specific items.

pointCPD

Risk assessment and risk register

Construction project

Doc no.
Revision
Page
__ of __

Identify hazards, assess the risks, control them using the hierarchy of control, and review. Keep this register current for the life of the project.

1. Scope

Project / siteClient
Scope of this assessmentWhole project, stage or activity
Prepared byDate
People consultedWorkers, subcontractors, HSR, designer

2. Risk rating matrix

Likelihood ↓ / Consequence →InsignificantMinorModerateMajorCatastrophic
Almost certainMHHEE
LikelyMMHHE
PossibleLMHHE
UnlikelyLLMHH
RareLLMMH
  • E Extreme: do not start. Eliminate or redesign the task before any work.
  • H High: work only with higher-order controls in place and a supervisor sign-off.
  • M Medium: controls in place, monitored during the task.
  • L Low: manage by routine procedures.

3. Hierarchy of control

Work from the top. 1 Eliminate the hazard. 2 Substitute with something safer. 3 Isolate people from the hazard. 4 Engineering controls such as guarding, extraction or edge protection. 5 Administrative controls: procedures, training, signage, supervision. 6 Personal protective equipment.

Levels 5 and 6 should support higher controls, not replace them. If the risk after controls is still high, change the method.

4. Risk register

#Activity / areaHazardWho could be harmed and howRisk beforeControls (highest order first)Risk afterOwnerSWMS / JSA ref
Example1Roof framing and sheetingFall from roof edge and through openingsRoofers and carpenters: serious injury or deathERoof edge protection installed before roof work; openings covered and marked; harness system where edge protection is impracticable; work only with SWMS in placeMSupervisorSWMS-03
Example2Site perimeterPublic entering site; neighbours' childrenMembers of the public: falls, struck by plantHSecure temporary fencing with lockable gates; signage with site contact; gates closed at end of day and checkedLSite managerSite rules

6. Review record

Review at each new stage, when work methods or trades change, after an incident or near miss, and if a control is not working.

DateReason for reviewChanges madeReviewed by

7. Approval

Approved byPosition
SignatureDate
Template by PointCPD · pointcpd.com.au/resources/templates/risk-assessment-template/Free to use, copy and adapt, including commercially (CC BY 4.0). Keep this credit line.v1.0

Download Word Download PDF

Questions builders ask

What is a risk assessment in construction?

A structured way of identifying hazards on a job, working out how likely and how serious the harm could be, and deciding what controls will eliminate or reduce the risk. It is the core of the WHS risk management process.

Is a risk assessment legally required?

WHS laws require businesses to manage risks, and a risk assessment is how you work out what controls are needed. For some hazards the regulations require a risk assessment specifically; for others it is the practical way to show you met the general duty.

What is a 5x5 risk matrix?

A grid that rates risk by combining five levels of likelihood with five levels of consequence, giving a rating such as low, medium, high or extreme. It is a common tool, not a legal requirement, and the labels vary between businesses.

What is the hierarchy of control?

The order in which controls should be considered: eliminate the hazard, substitute it, isolate it, use engineering controls, then administrative controls and PPE. Higher controls are more reliable because they do not depend on people doing the right thing every time.

How is a risk register different from a SWMS?

A risk register covers all the hazards across a project or business. A SWMS covers a specific high-risk construction activity and is the document workers follow on site. The register tells you which SWMS you need.

How often should a risk assessment be reviewed?

When the work, methods, site or people change, at each new stage of a project, after an incident or near miss, if a control is not working, and when workers or their representative raise a concern.

Free to use, adapt and share, including commercially

This template is licensed under Creative Commons Attribution 4.0. Copy it, rebrand it, edit it for your jobs, hand it to clients and subcontractors, or republish it. The one condition: keep the small PointCPD credit line on the document. If you publish it online, credit it like this:

<a href="https://pointcpd.com.au/resources/templates/risk-assessment-template/">Construction risk assessment and risk register template</a> by PointCPD, CC BY 4.0

Last reviewed 14 September 2026. A template is a starting point: it becomes a compliant document only once it is completed for the actual job by people who understand the work, and kept current as the work changes. General information, not legal advice. Check the requirements of your state regulator and your contract.

Sources: Model Work Health and Safety Act and Regulations (risk management and hierarchy of control). Safe Work Australia, Code of Practice: How to manage work health and safety risks and Code of Practice: Construction work.