Free template Inspections and quality

Free frame inspection checklist for timber and steel frames

Check a timber or steel frame before it is covered: wall frames, bracing, tie-downs, lintels, trusses and roof bracing, openings, fire separation and certifier sign-off.

The short version

Before the frame is covered, check it against the engineer's drawings, the truss layout and the framing standard: wall frames plumb and straight, bracing and tie-downs installed as designed, lintels and beams correctly sized and supported, trusses and roof bracing to the manufacturer's layout, and every opening, fixing and fire separation correct. In NSW the principal certifier's mandatory inspections include one before the framework is covered.

  • No sign-up
  • Free for commercial use
  • Add your own logo
  • Updated 14 Sep 2026

Reviewed by Daniel Betros, Licensed Building Practitioner

Animated walkthrough · 7 steps

How to inspect a frame

Seven steps, working from the slab up. Have the engineering, truss layout and bracing plan with you.

1 / 7
  1. Structural drawings, bracing and tie-down plans, the truss manufacturer's layout and certification, and the frame supplier's details. Check revisions match what was built.

  2. Frames fixed to the slab as designed, plumb, straight and square, studs and plates the specified size, noggings in place, no damaged or over-notched members.

  3. Every bracing wall and tie-down on the plan is actually there, fixed with the specified connectors and fasteners. This is where frames most often fail inspection.

  4. Lintels and beams to the specified size and bearing, jamb studs and packers under them, openings the right size for the windows and doors ordered.

  5. Truss spacing, positions and girder connections to the manufacturer's layout, truss tie-downs, roof bracing and binders installed, nothing cut or altered without approval.

  6. Fire separation in attached dwellings, wet area noggings, sarking and flashings where installed, and service holes within allowable limits.

  7. Certifier, engineer and truss certification recorded, defects fixed and re-checked, and photos taken before any lining or cladding goes on.

A frame looks finished long before it is. The bracing wall that was never sheeted, the tie-down that was left for later, the truss web cut to fit a duct: all of them look fine from the street, and all of them disappear behind plasterboard and cladding within days. The frame inspection is the last chance to see the structure of the house. This checklist goes through it from the slab up.

The documents come first

A frame can only be checked against something. Before walking the frame, have the structural drawings, the bracing and tie-down plans, the truss manufacturer’s layout and certification, and the wind classification for the site. Check the revisions match what was actually built: engineering is often revised after the frame is ordered, and the frame follows the old drawing.

For timber framing, AS 1684 is the deemed-to-satisfy standard under the National Construction Code for residential construction, used together with any engineering for the job. Light steel framing typically follows the NASH standard or project engineering. The checklist states no sizes or spacings: those come from those documents.

Mandatory inspection in NSW

For new houses, the NSW principal certifier’s mandatory critical stage inspections include one before the framework for any floor, wall, roof or other building element is covered. Book it before the wall wrap and lining trades are booked, not after, and do not let anyone cover the frame until it is done.

Bracing and tie-down: where frames fail

If a frame inspection finds a problem, it is most often here. Bracing resists racking: the wind pushing the walls sideways. Tie-down resists uplift: the wind lifting the roof off the walls and the walls off the slab. Both are designed as continuous load paths, and a single missing link breaks the chain. Go through the bracing and tie-down plans item by item: every bracing wall in the right place and length, fixed with the right fasteners, every tie-down connector installed, and hold-downs tightened.

Trusses

Trusses are engineered products. Their capacity depends on every web and chord being intact and on the bracing the manufacturer specifies. The common site failures are trusses cut or notched to fit ducts, skylights or plumbing, missing binders and roof bracing, and girder connections not installed as detailed. Any modification needs the manufacturer’s or engineer’s approval before it happens. Get the truss manufacturer’s certificate for the file.

The details that will be covered

DetailWhy check it now
Fire separationIn attached dwellings, separating walls must continue as detailed, typically to the underside of the roof. Gaps are a serious compliance and life-safety defect.
Wet area noggingsFixtures, grab rails and wall-hung vanities need solid fixing. Adding it later means opening the wall.
Blocking for the futureTV mounts, cabinetry and future grab rails are cheap to allow for now.
Service penetrationsHoles and notches outside allowable limits weaken studs and plates.
Flashings and wrapsWindow and door flashings installed wrong are a leading cause of water damage claims.

Defects: fix, re-check, record

Section 8 records every defect found, what was done, and when it was fixed. Re-check the fix before sign-off, and if the certifier found the defect, get their re-inspection or confirmation. Photograph the frame thoroughly before lining, especially bracing, tie-downs and fire separation. The next checkpoint is before plasterboard: use the pre-plasterboard checklist, and track every hold point with the inspection and test plan.

Timber and steel frames: different checks

AreaTimber framesLight steel frames
MembersSize and stress grade, treatment where required, moisture, splits and waneSection and gauge, coating undamaged, no kinks or crushed flanges
ConnectionsNailing, connectors and tie-down hardware to the plansScrews or rivets to the fabricator’s details, no missing fasteners
ServicesHoles and notches within limitsPre-punched service holes used, grommets fitted, no site-cut holes in critical zones
DurabilityClear of ground and moisture, termite protectionSeparation from incompatible metals and treated timber, corrosion protection at cut edges where required

The frame defects owners’ inspectors find most

Independent building inspectors engaged by owners at frame stage tend to find the same things. Knowing the list lets you find them first:

  • bracing sheets with missing or over-driven nails, and strap bracing not tensioned;
  • tie-down connectors missing at some trusses or not fixed with the specified nails;
  • jamb studs under lintels missing or not continuous;
  • truss webs cut or packed out without approval;
  • frames out of plumb or bowed, which shows later in linings and cabinetry;
  • wall frames not fixed to the slab at the specified spacing.

An owner’s report that lists these is uncomfortable. A builder’s own checklist that already fixed them is not.

Preview the full Frame inspection checklist template

Every section, field and check in the download, exactly as it prints. Edit the Word version to add your logo, delete what does not apply and add your own site-specific items.

pointCPD

Frame inspection checklist

Timber or light steel framing, before covering

Doc no.
Revision
Page
__ of __

Check against the structural drawings, bracing and tie-down plans, the truss manufacturer's layout, and the framing standard that applies (AS 1684 for timber, the NASH standard for light steel). Do not cover the frame until inspections are complete.

1. Project and documents

SiteFrame typeTimber, light steel, mixed
Structural drawings and revisionWind classification
Frame supplier / fabricatorTruss manufacturer and layout reference
Carpenter / framerInspection date

2. Wall frames

#CheckYesNoN/AComments / action
1Bottom plates fixed to slab with specified anchors at specified spacing
2Frames plumb, straight and square within tolerance
3Stud and plate sizes and grades as specified
4Stud spacing as specified
5Noggings installed as required
6Top plates joined and lapped correctly
7No over-notched, over-drilled or damaged members
8Load-bearing walls in the right positions under trusses and beams
9Timber moisture and treatment appropriate; steel protected from damage and corrosion

3. Bracing and tie-downs

Compare with the bracing and tie-down plans item by item.

#CheckYesNoN/AComments / action
1All bracing walls on the plan installed, in the right locations and lengths
2Bracing type as specified (sheet, strap, diagonal)
3Bracing fixings and nailing as specified
4Strap bracing tensioned and fixed at each end
5Wall tie-downs installed at specified locations
6Connectors and fasteners of the specified type and number
7Hold-down bolts or rods installed and tightened
8Engineered bracing or portal frames installed as detailed

4. Lintels, beams and openings

#CheckYesNoN/AComments / action
1Lintel sizes as specified for each span
2Adequate bearing at each end, with jamb studs as required
3Beams and girders sized, supported and fixed as detailed
4Point loads carried down to the foundation
5Opening sizes match windows and doors ordered
6Sill trimmers and heads level

5. Trusses and roof framing

#CheckYesNoN/AComments / action
1Truss positions and spacing to the manufacturer's layout
2Girder trusses and truss-to-truss connections as specified
3Truss tie-downs installed with specified connectors
4Top chord binders and roof bracing installed
5Bottom chord ties and restraint installed
6No truss cut, notched or modified without manufacturer approval
7Rafters, ridges and hips (stick framing) to specification
8Battens of specified size, spacing and fixing
9Truss manufacturer certificate received

6. Details that will be covered

#CheckYesNoN/AComments / action
1Fire separation walls in attached buildings built to underside of roof as detailed
2Wet area noggings for fixtures, grab rails and wall-hung fittings
3Blocking for cabinetry, TV mounts and future grab rails
4Sarking and wall wrap installed and lapped (if at this stage)
5Window and door flashings installed (if at this stage)
6Service holes and notches within allowable limits
7Termite management inspection zone kept clear
8Frame protected from weather

7. Inspections and certification

Inspection / certificateByDateResult / reference
ExamplePrincipal certifier: before covering framework
ExampleStructural engineer (if required)
ExampleTruss manufacturer certification

8. Defects and rectification

LocationDefectActionFixed (date)

9. Builder sign-off: frame ready to cover

NameSignature
DatePhotos taken?
Template by PointCPD · pointcpd.com.au/resources/templates/frame-inspection-checklist/Free to use, copy and adapt, including commercially (CC BY 4.0). Keep this credit line.v1.0

Download Word Download PDF

Questions builders ask

What is checked at a frame inspection?

Wall frames, bracing and tie-downs, lintels and beams, trusses and roof bracing, openings, connections, and details that will be covered such as fire separation and wet area noggings, all against the engineering, the truss layout and the framing standard.

Is a frame inspection mandatory in NSW?

For new houses, the NSW principal certifier's mandatory critical stage inspections include one before the framework for any floor, wall, roof or other building element is covered. The engineer may also require an inspection.

What are the most common frame inspection defects?

Missing or incorrectly fixed bracing and tie-downs, undersized or poorly supported lintels, trusses altered on site, missing roof bracing, and frames out of plumb. Most come from working to habit rather than the plans.

Can trusses be cut on site?

Not without the truss manufacturer's or engineer's approval. Cutting a web or chord to fit a duct or skylight can remove the truss's capacity entirely.

What standard applies to timber framing?

AS 1684 Residential timber-framed construction is the deemed-to-satisfy standard for timber framing under the NCC, alongside any engineering for the job. Light steel framing typically follows the NASH standard or engineering.

Why photograph the frame before lining?

Because bracing, tie-downs, noggings and fire separation disappear behind linings and cladding. Photos are the builder's evidence if the work is ever questioned, and they help trades find services later.

Free to use, adapt and share, including commercially

This template is licensed under Creative Commons Attribution 4.0. Copy it, rebrand it, edit it for your jobs, hand it to clients and subcontractors, or republish it. The one condition: keep the small PointCPD credit line on the document. If you publish it online, credit it like this:

<a href="https://pointcpd.com.au/resources/templates/frame-inspection-checklist/">Frame inspection checklist template</a> by PointCPD, CC BY 4.0

Last reviewed 14 September 2026. A template is a starting point: it becomes a compliant document only once it is completed for the actual job by people who understand the work, and kept current as the work changes. General information, not legal advice. Check the requirements of your state regulator and your contract.

Sources: Environmental Planning and Assessment Regulation 2021 (NSW), critical stage inspections. National Construction Code, Housing Provisions. AS 1684 Residential timber-framed construction and the NASH Standard for residential and low-rise steel framing (not reproduced). Engineer's drawings and truss manufacturer documentation govern.