Free RFI template (request for information) for construction

Ask the designer or client one clear question, with the drawing reference, a proposed solution, the date an answer is needed, and whether it affects cost or time. Includes a register.

The short version

An RFI asks the designer, engineer or client one specific question about the contract documents: a conflict, an omission or something unclear. Include the drawing or specification reference, a proposed answer, the date a response is needed to avoid delay, and whether it may affect cost or time. Log every RFI in a register. The dated question and answer are your evidence if the response becomes a variation or a delay.

  • No sign-up
  • Free for commercial use
  • Add your own logo
  • Updated 14 Sep 2026

Reviewed by Daniel Betros, Licensed Building Practitioner

Animated walkthrough · 6 steps

How to write an RFI that gets answered

Six steps. One question per RFI, and always offer an answer.

1 / 6
  1. Sequential RFI number, the project, and the right recipient: architect, engineer, certifier or client. Copy anyone whose work is affected.

  2. Drawing number and revision, grid line, detail, specification clause. The responder should not have to hunt.

  3. State what the documents say, what the problem is, and the question. One issue per RFI keeps answers clean and trackable.

  4. Suggest a solution: "Propose to use the detail on drawing A-501 at this junction." It speeds responses and shows you are solving, not stalling.

  5. The date an answer is needed to avoid delay, and whether the answer may affect cost or time. Flagging it now protects your position.

  6. Record who answered and when, whether it is a variation, and close it in the register. Chase anything overdue.

Every set of drawings has gaps: a detail that does not work at a corner, a dimension that does not add up, a product that is no longer made. The builder who asks about them early, in writing, avoids rework and keeps the right to be paid for the answer. The builder who guesses, or asks on the phone, often ends up paying for the difference. This RFI template turns the question into a record.

What an RFI is for

A request for information is a formal question from the builder to whoever controls the design: the architect, the engineer, the certifier or the client. Use it when the contract documents are:

  • conflicting, such as the architectural and structural drawings showing different beam sizes;
  • incomplete, such as a junction or finish not detailed;
  • unclear, such as a note that could be read two ways;
  • not buildable, such as a detail that does not work on site; or
  • overtaken, such as a specified product that is discontinued.

Anatomy of an RFI that gets answered quickly

PartWhy
NumberSo it can be tracked and referred to in variations and claims
Exact referenceDrawing, revision, grid, detail, clause: the responder should not have to search
One questionMultiple questions produce partial answers and confusion
Proposed answerOften the designer simply confirms it, which is the fastest response of all
Date neededTies the response time to your program and any delay
Impact flagRecords early that the answer may affect cost or time

RFIs and variations

An RFI response is not automatically a variation. If the answer changes the work, the price or the time, confirm it with a signed variation. The template says that a response is not an instruction to vary unless it is confirmed, which protects both sides from treating a clarification as a change. In NSW residential work, variations need to be in writing and signed by both parties, so the RFI is often the first step on the way to one.

RFIs and delays

If work is waiting on an answer, the delay may entitle you to an extension of time, depending on the contract. The RFI shows when the question was asked and when the answer was needed; the site diary shows the work that could not proceed. Together they are the evidence an extension of time claim needs. Check your contract for notice requirements: many require notice of a delay within a set period, whether or not the RFI has been answered.

Keep a register

Section 6 is a simple register: number, date, subject, recipient, date needed, date answered, and whether it became a variation. It shows at a glance what is outstanding and who you are waiting on. Review it at every site meeting and chase overdue RFIs in writing.

Informal is fine, unrecorded is not

On a small residential job, an RFI can be an email with a number, a clear question, a drawing reference and a date. What matters is not the format but that the question and answer are written, dated and kept. The phone call that settled a detail is worthless in a dispute; the email that confirmed it is not.

Examples of well-written RFIs

WeakClear
“Beam size?”“Architectural A-201 rev C shows a 290 mm deep beam over the family room opening; structural S-102 rev B shows 360 mm. Which applies? Proposed: structural S-102. Needed by 12 March for the frame order.”
“Tiles not available”“Specified floor tile (spec clause 9.2) is discontinued by the supplier. Proposed alternative attached with sample and data sheet; same size and slip rating. Please confirm acceptance or nominate another by 20 March to hold the tiling program.”

The clear versions give the reference, the problem, a proposed answer and the date that matters. They are answered faster, and they leave a record that explains any later cost or delay.

RFIs on design and construct jobs

On design and construct contracts, where the builder is responsible for completing the design, many questions are the builder’s to answer rather than the client’s. RFIs are still useful internally, between the builder and its designers and engineers, to record decisions. Questions that go to the client, such as selections, performance requirements or changes to the brief, should still be written, numbered and dated, because they are the ones most likely to become variations or delays.

Preview the full Request for information (RFI) template

Every section, field and check in the download, exactly as it prints. Edit the Word version to add your logo, delete what does not apply and add your own site-specific items.

pointCPD

Request for information

Query on the contract documents

Doc no.
Revision
Page
__ of __

One question per RFI. Include references and a proposed answer. A response to an RFI is not an instruction to vary the work unless it is confirmed as a variation.

1. RFI details

RFI numberDate issued
Project / siteFrom (builder)
ToArchitect, engineer, certifier, clientCopies to
Subject

2. Document references

Drawing number(s) and revisionDetail / grid / location
Specification clausePhotos or sketches attached?

3. Question and proposed answer

What the documents show
The problemConflict, omission, unclear, not buildable, product unavailable
Question
Proposed answer

4. Timing and impact

Response required byWork affected if late
Possible cost impact?Yes / No / UnknownPossible time impact?Yes / No / Unknown

5. Response

Response
Responded byDate received
Variation required?If yes, variation numberClosed by / date

6. RFI register

No.DateSubjectToNeeded byAnsweredVariation?
Template by PointCPD · pointcpd.com.au/resources/templates/rfi-template/Free to use, copy and adapt, including commercially (CC BY 4.0). Keep this credit line.v1.0

Download Word Download PDF

Questions builders ask

What is an RFI in construction?

A request for information: a formal written question from the builder to the designer, engineer or client about the contract documents, used when something is unclear, missing or conflicting.

When should I issue an RFI?

As soon as you find a conflict, omission or unclear detail, well before the work is due. Late RFIs cause delays that are harder to claim.

Is an RFI response a variation?

Not automatically. If the answer changes the contract work, price or time, it should be confirmed as a variation in writing. Say on the RFI that a response is not an instruction to vary unless confirmed.

Why include a proposed answer?

It speeds up responses, often the designer just confirms it, and it shows the builder is solving the problem rather than creating a claim.

Do small residential builders need RFIs?

Yes, even informally. An email with a number, a clear question and a date is an RFI. What matters is that the question and answer are recorded and dated.

What if an RFI is not answered in time?

Chase it in writing, record the delay in the site diary, and check your contract for extension of time and notice provisions. The RFI register shows when you asked.

Free to use, adapt and share, including commercially

This template is licensed under Creative Commons Attribution 4.0. Copy it, rebrand it, edit it for your jobs, hand it to clients and subcontractors, or republish it. The one condition: keep the small PointCPD credit line on the document. If you publish it online, credit it like this:

<a href="https://pointcpd.com.au/resources/templates/rfi-template/">Request for information (RFI) template</a> by PointCPD, CC BY 4.0

Last reviewed 14 September 2026. A template is a starting point: it becomes a compliant document only once it is completed for the actual job by people who understand the work, and kept current as the work changes. General information, not legal advice. Check the requirements of your state regulator and your contract.

Sources: Construction contract administration practice. Your building contract sets how instructions, variations and extensions of time are handled.